Chapter Ashburton Update
Stay informed with our latest construction updates.
29 November 2023
November Construction Update
- Level 1 concrete slab pour 1 and 2 complete.
- Level 2 concrete slab pour 1 and 2 complete.
- The entire concrete structure was completed. This includes concrete and pre-cast elements.
- Installation of hobs complete.
- Lightweight steel installation to level 2 commenced.
47.48% completed
31 October 2023
October Update
- Level 1 slab pour 1 and 2 complete.
- Level 2 slab pour 1 complete.
- Building Permit 3 received.
- Pre-cast panel installation commenced.
43.9% completed
1 September 2023
September Update
25.51% completed
1 August 2023
August Construction Update
8.41% completed
1 July 2023
July Update