Chapter Ashburton Update
Stay informed with our latest construction updates.
18 June 2024
April & May Construction Update
- Tiling and joinery installed.
- Benchtops, splashbacks and mirrors installed.
- Bathroom fixtures and hardware installed.
- Fit-out to services complete.
- Appliance installation commenced.
- Robes and showers installed.
96.32% completed
4 April 2024
March Construction Update
- Cladding complete
- Plaster complete
- Waterproofing complete
- Tiling and joinery installation commenced.
- Painting commenced.
85.6% completed
29 February 2024
February Construction Update
- Full concrete structure including pre-cast panel installation complete.
- Light Weight Steel installation on level 2 is complete.
- Fire and Mechanical rough-in to the basement and ground floor are complete.
- Installation of windows and balustrades complete.
- Ground Floor and level 1 walls plastered. (level 1 ceilings 50%).
78.16% completed
19 February 2024
January Construction Update
- Roof installed
- Windows and Balustrades installed
- Installation of mechanical exhaust and sprinkler droppers
- Subhead and Subsill complete
68.6% completed
21 December 2023
December Construction Update
- Level 2 lightweight steel installation completed.
- Fire and mechanical service rough-in to the basement and ground floor commenced.
- Subhead and subsill installation commenced.
- Structure concrete pre-cast elements completed.
- Preparation for roof installation commenced.
- Strip out of 80% of all floors complete.
53.7% completed
29 November 2023
November Construction Update
- Level 1 concrete slab pour 1 and 2 complete.
- Level 2 concrete slab pour 1 and 2 complete.
- The entire concrete structure was completed. This includes concrete and pre-cast elements.
- Installation of hobs complete.
- Lightweight steel installation to level 2 commenced.
47.48% completed
31 October 2023
October Update
- Level 1 slab pour 1 and 2 complete.
- Level 2 slab pour 1 complete.
- Building Permit 3 received.
- Pre-cast panel installation commenced.
43.9% completed
1 September 2023
September Update
25.51% completed
1 August 2023
August Construction Update
8.41% completed
1 July 2023
July Update
1 June 2023
June 2023
1 May 2023
May 2023